Saturday, March 28, 2009

End of Week 3

Tasks accomplished for the week:

  • Worked on SRS - 5 hours - Full team
    • Summary
    • Users
    • Use Cases
    • Usability Requirements
    • HTAs
    • Prototype screens
  • User classes and layout brainstorming - 1 hour - Full team
  • Splitting up project for prototype implementation - .5 hour - Full team
  • Exploration of Flex capabilities and limitations - 2 hours - Full team
  • Created working 'flex image -> email' web service using PHP - 5 hours, Rob
  • Performance enhancements in prototype drawing code - 1 hour, Rob
  • Create icons for the GUI - 2 hours - Dan
  • Create working on screen keyboard for the email screen - 2 hours - Dan
  • Blog Posting .5 - Rob
Tasks to focus on next week:

  • Integration of 'email' and 'drawing' screens in functional prototype (evolutionary) ~ 2 hours - Matt B
  • Preparation for cognitive walkthrough ~ 1 hour - Full team
  • Begin a concise Design document for project using the provided template ~ 2 hours - Full team
  • User session implementation ~ 2 hours - Rob

Challenges and Issues:

  • Matching HTA's to a common style for the SRS
  • Defining how to best present the capabilities to a new user. One good idea that developed was to explicitly ask the user if they had used the program before.