Tasks accomplished for the week:



  • Complete Project Deliverable 4a for Monday - 4 hours - Full Team

  • Confirm that email went through- send boolean back from php script - 2 hours- Matt B.

  • Correct interaction of tool menu with undo button - 2 hours - Rob

  • Icons for everything -5 hours - Dan

  • Better Welcome Screen - 1 hour - Matt K.

  • Stamp functionality -3 hours- Rob

  • Custom cursors (art) - 2 hours - Dan, Matt B.

  • Custom cursors (code) - 1 hour - Matt K.

  • Deployment of project to server for review - 1 hour - Matt B.



Tasks to focus on next week:



  • Conduct User Testing! - 10 hours - Full Team


    • Setting up for testing

    • Conducting testing

    • Administering Surveys

    • Aggregating Data



Challenges and Issues:


Due to an oversight on our part, a setting was changed which disallowed Flash from entering full screen mode. This caused minor confusion while getting the final code ready to go, for the Friday deadline.