Tasks accomplished for the week:
Pre-testing prototype modifications:- Stamp images added and 'undo' behavior fixed when used after placing stamps - 2 hours - rob
- Toolmenu behavior tweaks - 2 hours -rob
- Email screen colors enhanced for readability - 0.25 hours - dan
- 'Erase All' button moved and recolored - 0.5 hours - dan
- higher JPG quality for screenshots - 0.25 hours - rob
Conducted User Testing:
- Set up for testing - 1 Hour - Dan and Rob
- Conduct testing & Administer Surveys - 2 Hours - Full Team
Tasks to focus on next week:
- Conduct Additional Testing (if needed) - 1 Hour - Full Team
- Aggregate Data - 2 Hours - Rob and Matt K.
- Begin Analyzing Results - 2 Hours - Dan and Matt B.
- Start final Presentation - 2 Hours - Full Team
Challenges and Issues:
- Configuring stable wiimote input for testers. (Required experimentation with sensor placement and location of tester)
- Finding particpants willing to participate in the usability testing.